If you are putting SPC flooring over an existing concrete slab or old tile in a Maritime basement, the first decision is not the colour. It is the install method. Click-lock floating and glue-down are two different jobs with two different subfloor rules, and buying the wrong product for your method is the most expensive mistake a first-time retrofitter makes. We sell both, we do not install either, and this guide is written so you can buy the right one.
The subfloor decides the method before you do
Both methods fail at the same place: an uneven or wet slab. But they fail differently, and the tolerances are not the same.
Glue-down is unforgiving on flatness. The adhesive bed is thin, so every high spot and low spot in the slab telegraphs straight through the plank. Glue-down also demands a dry slab. Under ASTM F710 (Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring), concrete moisture vapor emissions must not exceed 3 lbs per 1,000 sq ft per 24 hours on the calcium chloride test (ASTM F1869), or 75% relative humidity on the in-situ probe test (ASTM F2170). That is per ASTM International. In an older Maritime basement, you test for that number — you do not assume it.
Click-lock floating is more tolerant of a slab that is level but not perfect, because the planks lock to each other rather than to the floor. It is not tolerant of a slab that dips and rolls — a floating floor over a wavy slab flexes at every joint and eventually clicks apart. The honest limitation: neither method rescues a bad slab. One of them just hides a slightly worse one.
Moisture barriers in a Maritime basement
This is where our region changes the math. A below-grade slab here moves moisture year-round, and the ASTM F710 numbers above are the reason you cannot skip the test. For a floating click-lock install over concrete, a separate 6-mil poly moisture barrier under the floor is standard practice; many SPC planks carry an attached IXPE pad, but an IXPE pad is acoustic, not a vapor barrier, and the two jobs should not be confused.
Glue-down over a damp slab is a different problem entirely. If the slab reads above the ASTM F710 threshold, the adhesive bond is compromised and no product claim fixes that. We would rather lose a sale than sell you glue-down for a slab that has not been tested and passed.
What click-lock actually gains you
Reversibility. A floating floor can be lifted, a damaged plank swapped, and the floor put back down — useful in a rental or a basement you may finish differently later. It also installs faster with no cure time, so the room is usable the same day.
The mandatory cost of that freedom is expansion space. Per the SPC Tri-Core Click Installation Instructions (manufacturer specification under the ASTM F710 framework), a click-lock floating floor needs a perimeter expansion gap of at least ¼ inch (6 mm) in a standard room, widening to ½ inch (12.7 mm) for areas over 50 ft × 50 ft (2,500 sq ft), plus an added expansion joint on long runs. Skip the gap and the floor has nowhere to go when it moves — it peaks at the joints. We get this call every spring. The gap is not optional; it is the whole reason the method works.
Where glue-down earns its price
Glue-down is not the premium option by accident. It earns its cost on commercial, high-traffic floors: a retail entry, a clinic corridor, a shop floor. A fully bonded plank does not shift under rolling loads, does not drum underfoot, and handles point loads from carts and chairs better than a floating floor. There are no expansion gaps breaking up a big open run, and the floor stays dead flat under furniture that never moves.
For a hallway that sees fifty people a day, glue-down is the right buy. For a spare basement bedroom, it is cost you do not need to spend. We publish that trade-off plainly because it decides which product you order.
Why the method matters more in 2026
Atlantic Canada is building. Full-year 2025 CMHC data shows regional housing starts reached 16,856 total units, up 20% from 13,998 in 2024, with multi-unit starts driving the gain at 13,173 units — a 25% jump, per CMHC. Multi-unit means more suites, more corridors, and more floors where the install method is a spec decision, not a preference. A corridor wants glue-down; a suite interior usually floats.
Material cost is also tighter. The Canadian Construction Association notes counter-tariffs that took effect in September 2026 touched a wide range of building inputs. That is one more reason to buy the right method once rather than tear out the wrong one later.
How we sell it
We import our SPC directly — one importer, one contact. We buy each line from the factory that makes it well — in Europe where that is Europe, elsewhere where it is not. You get the trade price from one unit with an approved trade account (free; a business name and HST/business number, approval within 1 business day), or from two units without one; the retail price applies to a single unit for anyone. Warranty terms are in writing before you buy, not after. We publish the actual numbers, including the ones that cost us a sale — like telling you to test your slab before you order glue-down.
Key Takeaways
- Test the slab first. ASTM F710 caps concrete moisture at 3 lbs/1,000 sq ft/24 hr (ASTM F1869) or 75% RH (ASTM F2170) — glue-down over a wetter slab fails.
- Click-lock floating is reversible and installs same-day, but needs a ¼ inch (6 mm) perimeter gap — ½ inch (12.7 mm) over 2,500 sq ft — per the Tri-Core Click spec.
- Glue-down earns its cost on high-traffic commercial floors; it is overspend for a quiet basement room.
- An IXPE pad is acoustic, not a vapor barrier — a Maritime basement still needs a separate moisture barrier under a floating floor.
- Buy the product that matches the method — not the other way around.
Next step
Tell us the room, the subfloor, and whether you have a moisture number for it, and we will point you to the SPC line and method that fit — no install service, just the facts and the right product. Trade accounts are free and approved within one business day at vybuild.ca/trade-account/.